Construction progress 09/01/2020
The installation of the rafter system in the house 14/39 has been completed. Laying of power cables and cables for Internet and television is underway. A fence is being installed on the site. Partitions are being installed in houses 14/36, 14/37, 14/38. The laying of the gas block in the house 14/40 continues. The entrance group is ennobled. Finished painting the fence. Planning works are being carried out on the roadway.