Construction progress 02/08/2021

Work is being carried out to arrange the foundation of house number 14/31 – reinforcement of the foundation sole with concrete laying. In houses 14/37, 14/38, 14/39, the roof is insulated. In houses 14/40, 14/41, the installation of crates and hydraulic barriers is underway. In houses 14/37, 14/38, 14/39, the laying of partitions is being completed. Internal plumbing and electrical works are being carried out in buildings 14/37, 14/38, 14/39.